On Friday, February 5, one man died and three were injured when a 565-foot crane toppled in gusty winds in lower Manhattan, not far from the World Trade Center. The investigation will likely take weeks to months as experts try to reconstruct whether the engineering, erection, operation or manufacture of the crane, or some combination

It has long been the case that the California Air Resources Board (“ARB”) and each of California’s local Air Quality Management Districts (“AQMDs”) may regulate sources of portable emissions. However, about two decades ago, the legislature recognized that it was often impractical and too costly for businesses traveling throughout the state to acquire permits for

Interpreting Utah’s former mechanic’s lien statute, the Utah Court of Appeals has held that a contractor that contracted with and provided construction services for a developer could not maintain a valid mechanic’s lien on property owned by a third-party landowner. In Reeve & Associates, Inc. v. Tanner, 2015 UT App 166 (2015), the owners of

On November 9, 2015, Division One of the Court of Appeals affirmed a 2012 King County trial court judgment that joint-venture tunneling contractor Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper (VPFK) was liable to King County for $144 million in damages and attorney fees.

The case arose from the Brightwater project, a wastewater treatment plant north of Woodinville with a tunnel system that conveys wastewater to the plant and treated water to a marine outfall in Puget Sound. VPFK was awarded a $212 million contract to build two segments of the 13-mile tunnel system. Unfortunately, VPFK’s two tunnel-boring machines broke down several hundred feet beneath Lake Forest Park and Bothell. The machines required extensive repairs that threatened to delay the completion of the overall project.

VPFK repaired one machine and completed one tunnel segment, but King County did not accept the lengthy delay and additional cost proposed for the repair of the second machine. King County hired Jay Dee Coluccio to complete the remaining tunnel segment between Shoreline and Lake Forest Park. The Brightwater project began full operation in late 2012.

King County sued VPFK and its sureties for approximately $156 million, based on its costs arising from project delays and design modifications. VPFK counterclaimed for approximately $70 million, arguing that its delays were excused by differing site conditions and defective project design. King County acknowledged some of VPFK’s claims totaling about $4.7 million.

After a nearly three-month trial, the jury awarded $156 million in damages to King County, offset by $26 million to VPFK for its counterclaims. The court awarded King County its attorney/expert fees in the approximate amount of $14 million, for a net judgment of $144 million.

The trial and appeal involved a number of interesting issues, two of which are summarized here.

Joint checks are a useful tool in the construction industry to give owners and prime contractors peace of mind that lower-tier subcontractors or suppliers are being paid and potential lien claims are avoided.  But joint check agreements and the subsequent actions can result in unintended consequences and liability. In my recent article for the Daily

In addition to streamers and fireworks, the new year is occasioned by another tradition:  new laws.  Several new laws affecting Oregon contractors and developers took effect on January 1, 2016.

Paid sick leave:  Most Oregon construction employers must now provide employees with one hour of paid sick leave for every 30 hours worked.  Employees

It will happen to almost every contractor at some point — an owner or project developer will try to sue you.  Hopefully your insurer agrees you are covered, and you’ve dodged a bullet. But if your insurer tells you that you are not covered, things get sticky.  One common strategy is for the parties to

Subcontractor default is a construction project nightmare that can result in significant additional costs and delay completion of the project. But there are two chief options to protect against such risks — performance bonds and subcontractor default insurance.  In my recent article for the Daily Journal of Commerce, I outline the unique characteristics of

Developing public projects in Oregon requires an understanding of the Oregon Public Contracting Code and the complexities of procurement requirements. In my recent article for the Daily Journal of Commerce, I discuss four facets of public contracting that can help you successfully navigate the procurement terrain.  Read the full article here.

“Public Contracting

The increasing presence of liability waivers in construction and design contracts is of concern to owners, general contractors and architects alike.  In my recent article for the Daily Journal of Commerce, I address a variety of clauses that limit liability and offer tips for negotiating more reasonable conditions and limits.  Read the full article