The new RCW 39.04.360, effective June 6, 2024, outlines protections and payment assurances for contractors, subcontractors, and suppliers involved in public and private construction projects in Washington. This statute mandates timely issuance of change orders for undisputed additional work, imposes interest on delays, and clarifies the rights of aggrieved parties to seek appropriate relief, including
Bart Reed
Bart Reed is a partner in the firm’s Seattle office and practices with the Real Estate and Construction group. With extensive experience in complex commercial and construction law, multistate litigation and ADR (representing clients in 28 states), Bart focuses his practice on construction and design issues and disputes, representing owners, developers, contractors, subcontractors, design professionals and sureties, in diverse matters on both public and private projects. His experience covers a wide range of issues affecting design and construction clients, including contract drafting/negotiation, non-payment and surety claims, construction liens and payment bond claims, design disputes, construction defects, and scheduling issues in the defense and prosecution of delay/impact claims.
Click here for Bart Reed's full bio.
WSBA Construction Law Section Midyear CLE Program
On June 14, 2024, the WSBA Construction Law Section is hosting its midyear CLE program, “Back to the Future: Leveraging Technology in Post-Covid Construction Disputes,” which will cover ethics, construction-related case law updates, technology, perspectives from the bench, arbitration, artificial intelligence, and legislative updates and appeals.
As part of the program, my colleague Colm Nelson…
On Notice: Why Notice and Claim Procedures in Construction Contracts Matter
Construction contracts generally outline when and how contractors should notify parties about potential claims for additional compensation and/or time. These provisions are intended to provide project stakeholders with the information necessary to address unforeseen circumstances and streamline claim resolutions within the project rather than resorting to legal actions. However, in some cases, the contract provisions…
New Washington Law Applies Limitations to Retainage on Private Construction Projects
In the construction industry, “retainage”—the practice of withholding by an owner or contractor a portion of the funds that are due to a contractor or subcontractor for a construction project until its completion—is a term frequently negotiated in contracts for private construction projects as a means to mitigate the risk of default since the monies…
Considerations for Contesting a Frivolous Lien in Washington
For any owner or developer of a private construction project—and especially those looking to refinance or sell the property—lien claims can pose serious challenges as well as being a source of great frustration. In my latest column for the Daily Journal of Commerce, I outline some legal options for a Washington construction project owner…
Construction Law Updates, Public Works Issues, and Judicial Perspectives on Litigation in an Evolving Courtroom
On June 10, I will be co-chairing and my colleague Colm Nelson will be a panelist during the annual mid-year WSBA Construction Law Section CLE. This program is a full-day webinar presented by the WSBA in partnership with Stoel Rives and will cover construction law updates, public works issues, and judicial perspectives on litigation in…
Construction Contract Termination Provisions: Recent Washington Case Examines Parties’ Rights
The importance of carefully drafting, and following, a construction contract’s termination provisions was made clear for project owners and contractors by a recent Washington Supreme Court decision, Conway Construction Co. v. City of Puyallup. The city contracted with Conway to build a major roadway, but when the city lost confidence in Conway’s work, it issued…
Webinar: Navigating a Financially Troubled Project During Uncertain Times
On June 11, I will be co-chairing and my colleague Colm Nelson will be a panelist for “Navigating a Financially Troubled Project During Uncertain Times,” a full-day webinar presented by the WSBA Construction Law Section in partnership with Stoel Rives. Colm will be on a panel that will cover claims and claim defenses related to…
New Washington Case Strictly Construes Lien Statute and Rejects Warranty Work as Basis to Extend Lien Filing Period
In its March 11, 2021 opinion, Division Three of the Washington Court of Appeals considered whether the 90-day period to record a claim of lien is extended by a contractor performing work after substantial completion to correct nonconforming work – usually referred to as “warranty work.” In the case of Brashear Electric, Inc. v. Norcal Properties, LLC, the Court strictly construed the statutory term “repairing” to exclude the contractor’s correction of its own work and rejected the notion that warranty work extended the 90-day timeframe to file a lien claim.
Norcal Properties, LLC (“Norcal”) and Blue Bridge Properties, LLC (“Blue”) own adjacent properties. Norcal and Blue separately contracted with Vandervert Construction (“Vandervert”) to construct a building on each property. The prime agreements’ substantive provisions were identical. Vandervert subcontracted with Brashear Electric, Inc. (“Brashear”) to work on both projects.
Under the prime agreements, Vandervert promised to correct nonconforming work up to a year after substantial completion. Vandervert’s subcontracts with Brashear required Brashear to assume the prime agreements’ warranty provisions.
Mitigation of Risk in the Age of COVID-19: Ten Ways Owners Can Protect Themselves Against Lien Claims in Washington
Among the many effects on the U.S. economy of the COVID-19 pandemic, construction projects that started before it began but were halted in its aftermath may be slow to resume or be abandoned altogether thanks to funding issues. Contractors, subcontractors, and suppliers feel immense pressure to protect and preserve their rights to payment for work…