For any owner or developer of a private construction project—and especially those looking to refinance or sell the property—lien claims can pose serious challenges as well as being a source of great frustration. In my latest column for the Daily Journal of Commerce, I outline some legal options for a Washington construction project owner
Oregon law requires a lien claimant to perfect its lien by recording it within 75 days of ceasing to “provide labor, rent equipment, or furnish materials or 75 days after completion of construction, whichever is earlier.” An unpaid contractor must record its lien 75 days after completion of its major contract work and removal of