If you dislike negotiating, you are not alone. But successful negotiators understand and embrace the opportunities that a negotiation presents.  In my recent article for the Daily Journal of Commerce, I discuss seven habits of successful negotiators that can help you successfully conclude your construction-related negotiations. Read the full article here

 “Hate Negotiating?

On Friday, February 5, one man died and three were injured when a 565-foot crane toppled in gusty winds in lower Manhattan, not far from the World Trade Center. The investigation will likely take weeks to months as experts try to reconstruct whether the engineering, erection, operation or manufacture of the crane, or some combination

It has long been the case that the California Air Resources Board (“ARB”) and each of California’s local Air Quality Management Districts (“AQMDs”) may regulate sources of portable emissions. However, about two decades ago, the legislature recognized that it was often impractical and too costly for businesses traveling throughout the state to acquire permits for

On November 9, 2015, Division One of the Court of Appeals affirmed a 2012 King County trial court judgment that joint-venture tunneling contractor Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper (VPFK) was liable to King County for $144 million in damages and attorney fees.

The case arose from the Brightwater project, a wastewater treatment plant north of Woodinville with a tunnel system that conveys wastewater to the plant and treated water to a marine outfall in Puget Sound. VPFK was awarded a $212 million contract to build two segments of the 13-mile tunnel system. Unfortunately, VPFK’s two tunnel-boring machines broke down several hundred feet beneath Lake Forest Park and Bothell. The machines required extensive repairs that threatened to delay the completion of the overall project.

VPFK repaired one machine and completed one tunnel segment, but King County did not accept the lengthy delay and additional cost proposed for the repair of the second machine. King County hired Jay Dee Coluccio to complete the remaining tunnel segment between Shoreline and Lake Forest Park. The Brightwater project began full operation in late 2012.

King County sued VPFK and its sureties for approximately $156 million, based on its costs arising from project delays and design modifications. VPFK counterclaimed for approximately $70 million, arguing that its delays were excused by differing site conditions and defective project design. King County acknowledged some of VPFK’s claims totaling about $4.7 million.

After a nearly three-month trial, the jury awarded $156 million in damages to King County, offset by $26 million to VPFK for its counterclaims. The court awarded King County its attorney/expert fees in the approximate amount of $14 million, for a net judgment of $144 million.

The trial and appeal involved a number of interesting issues, two of which are summarized here.

Subcontractor default is a construction project nightmare that can result in significant additional costs and delay completion of the project. But there are two chief options to protect against such risks — performance bonds and subcontractor default insurance.  In my recent article for the Daily Journal of Commerce, I outline the unique characteristics of

Developing public projects in Oregon requires an understanding of the Oregon Public Contracting Code and the complexities of procurement requirements. In my recent article for the Daily Journal of Commerce, I discuss four facets of public contracting that can help you successfully navigate the procurement terrain.  Read the full article here.

“Public Contracting

The increasing presence of liability waivers in construction and design contracts is of concern to owners, general contractors and architects alike.  In my recent article for the Daily Journal of Commerce, I address a variety of clauses that limit liability and offer tips for negotiating more reasonable conditions and limits.  Read the full article

There are inherent risks in proceeding to trial by jury. Juries are often unpredictable, and civil litigation also requires extensive discovery and motions practice, which can delay resolution and increase uncertainty and costs. Arbitration has long been accepted as the answer to these problems. But the changing nature of disputes, increasing costs and inefficiencies have

Many development projects have a federal connection — such as a federal permit or grant — that triggers compliance with Section 106 of the National Historic Preservation Act.  Section 106 requires the approving federal agency to assess the impacts of the development on properties that are listed or eligible for listing on the National Register

In the haste to get design and construction moving on real estate projects, one may lose sight of important lien priority issues when negotiating and executing contracts. In my recent article for the Daily Journal of Commerce, I discuss a notable Washington appellate case that addresses a lien priority issue in the context of