The Oregon Supreme Court will review two recent Court of Appeals decisions related to statutes of limitation and repose on construction projects. In the first case, Sunset Presbyterian Church v. Brockamp & Jaeger, Inc., the Oregon Supreme Court will address the following questions: (1) When the construction contract includes an accrual provision, is the

On September 26 and 27, 2013, The Seminar Group will present its 18th Annual Oregon Construction Law seminar in Portland, Oregon. I will be speaking about Integrated Project Delivery, which is an emerging project delivery method emphasizing collaboration among project participants. Three of my partners also will be presenting: Guy Randles, program co-chair, will speak

Washington’s lien laws, like those of other states, set forth pre-claim notice requirements that, if not satisfied, may result in the forfeiture of lien rights. The applicable statute, RCW 60.04.031, presents an interesting array of “if-then” scenarios in which the notice requirements are imposed. Generally, unless falling under one of three exempted categories, RCW 60.04.031

The Oregon Court of Appeals recently applied the so-called “economic loss rule” to a construction dispute (Marton v. Ater Construction Co., 256 Or App 554, __ P3d __ (2013)). Among other issues, the court decided whether the prime contractor’s negligence claim against its subcontractor was barred under the economic loss rule.

Under the

In my latest Daily Journal of Commerce Construction column, I discuss the need to know Oregon construction contracting law to avoid unwanted consequences. In Oregon, construction contracts are subject to a wide variety of legal requirements, many of which are often ignored or, in some cases, violated with disastrous results. Following link will provide a summary

Oregon Senate Bill 254A and the CMGC method generally garner more attention than is justified. Here is the background.

On a typical non-CMGC project, the general contractor will bid on a complete or nearly complete set of design documents. This is referred to as “design-bid-build.” In public construction, competitive bidding is required by statute to reduce expenditure of taxpayer funds. In the CMGC method, rather than awaiting a complete design, the contractor is chosen early and asked to (1) review the developing design of the architects and engineers, and (2) perform certain other planning and organizational work that theoretically benefits the project. The “early” work is generally considered the “CM” portion of the CMGC scope, while the post-bid or post-GMP (guaranteed maximum price) work is generally considered the “GC” portion.

What is so different about this process? Not much, really, but there are a couple of considerations that differ from traditional design-bid-build. First, because the CMGC is chosen before design is complete, the CMGC is not able to provide concrete pricing at the time it is selected; by the time the design is sufficiently complete to allow pricing, the CMGC has already been chosen. Critics argue (accurately) that this dynamic puts more leverage in the hands of the CMGC during price negotiations because the owner has now invested time and CM dollars in the CMGC and probably does not want to manage a second-round selection process to get a new contractor if the original CMGC’s price is not competitive. While this poses a theoretical problem for owners, the CMGC provides its percentage fee (markup) at the time of selection and is required to competitively bid all subcontractor work, reducing if not eliminating the concerns over cost control and negotiating leverage.

Can parties waive both the commencement and length of the statutory limitation periods for construction defect actions?  Yes, answered the Fourth Appellate District, by allowing the parties to contractually preclude the application of the “delayed discovery” rule that normally triggers the commencement of the limitation time period and affirming case law permitting the shortening of the 10-year latent limitation period to four years.  The court did hold, however, that such waiver and shortening is permitted where there are sophisticated parties, in a commercial context, and perhaps that the contract must even be highly negotiated (or at least such negotiation is available).

On June 3, 2013, in Brisbane Lodging, L.P. v. Webcor Builders, Inc. (Cal. Ct. App., June 3, 2013, No. A132555) 2013 WL 2404154, the appellate court reviewed the trial judge’s granting of summary judgment in favor of the general contractor (“Webcor”) on the grounds that a provision in the 1997 version of the AIA 201 (General Conditions to the prime agreement between Owner and Contractor) unambiguously barred all claims, contract and tort, brought more than four years after substantial completion of the project, rather than four years after the Owner discovered the alleged breach or defect and within the 10-year statute of repose.  The key language for both the trial court and the appellate court was found in provision 13.7:

“13.7 Commencement of Statutory Limitation Period

“13.7.1 As between the Owner and Contractor:

“.1 Before Substantial Completion. As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion ….” (AIA A201, Article 13.7.1.1 (Article 13.7.1.1), bolding and capitalization omitted.)

A 2013 decision from New York reminds us that threats can be costly. In Mometal Structures, Inc. v. T.A. Ahern Contractors Corp., from the Eastern District of New York, Mometal was hired by Ahern as structural steel subcontractor. The project was delayed for reasons that were not Mometal’s fault. Mometal tried to get the information and approvals

The Washington Supreme Court—in Gandee v. LDL Freedom Enterprises, Inc., 176 Wn.2d 598 (2013)—recently examined the validity and enforceability of a contractual arbitration provision and found, under the circumstances, that the clause was “unconscionable” and therefore unenforceable. Although the case did not occur within a construction setting, it nevertheless presents important lessons to consider when drafting, negotiating or complying with mandatory arbitration provisions in construction agreements.  

In Gandee, a borrower, under a debt adjustment contract, brought suit against LDL Freedom Enterprises, Inc. (“Freedom”), seeking to recover damages based on alleged violations of the Washington Consumer Protection Act (the “CPA”) (RCW 19.86, et seq.) and the Debt Adjusting Act (RCW 18.28, et seq.). Id. at 601-02. Freedom moved to compel arbitration based on the following arbitration clause reflected in the parties’ agreement:

Arbitration. All disputes or claims between the parties related to this Agreement shall be submitted to binding arbitration in accordance with the rules of [the] American Arbitration Association within 30 days from the dispute date or claim. Any arbitration proceedings brought by Client shall take place in Orange County, California. Judgment upon the decision of the arbitrator may be entered into any court having jurisdiction thereof. The prevailing party in any action or proceeding related to this Agreement shall be entitled to recover reasonable legal fees and costs, including attorney’s fees which may be incurred.

Id. at 602 (brackets in original). In addition, the agreement contained a common “severability clause,” providing that “[i]f any of the above provisions are held to be invalid or unenforceable, the remaining provisions will not be affected.” Id