A California appellate court recently held that the value of an original construction contract is admissible as evidence to limit a contractor’s right to recovery under Civil Code section 3123(a), even by a property buyer that was not a party to the construction contract. Appel v. Los Angeles Superior Court (CA No. B244590, Mar. 11, 2013). The net effect in this instance could be a reduction of the value of the contractor’s lien claim by at least $13.5 million. 

The underlying facts reflect an all-too-common scenario of a failed project. Here, a single-purpose entity developed a large condominium project, originally inked with a GMP of $65 million. Increases through construction by approved change orders moved the GMP to $81 million. Disputes arose, and the contractor thereafter claimed an additional $13.5 million above the $81 million GMP. Unfortunately here, several units of the project had been purchased by this point, and the buyers were then subject with the developer to the mechanic’s lien of the contractor. Prior to trial, the developer entity and its alter ego affiliates negotiated a pre-trial settlement with the contractor that included in part a restatement of the final contract GMP to $95.5 million, purportedly settling the issue of the “value” of the construction contract for the contractor to continue pursuing its lien claim against the unit buyers. During pre-trial motions, the trial court commented on the impact of the negotiated settlement and “expressed doubt as to whether the unit owners should be precluded from challenging the value of the GMP contract set forth in the settlement agreement:

 

COURT: Are you saying [the unit owners] don’t have a right to attack the . . . value of the contract which was agreed after the fact as part of the settlement?

[CONTRACTOR]: We don’t believe they have a right to attack that.

COURT: Well, that is just boggling to my mind. [¶] . . . [¶] [I]t totally boggles my mind, because you could agree to anything, anything [in the settlement].”

 

The trial court also stated that it saw “‘no purpose’ for the settling parties’ decision to raise the value of the GMP other than to hinder the unit owners’ lien foreclosure defense.” Although the trial court took the matter under submission, it later felt constrained to rely on an existing decision cited by neither party and ruled against the unit buyers, precluding them from challenging the post-lien GMP value set during the settlement between the developer and contractor.

In my latest Daily Journal of Commerce Construction column, I discuss the stop notice remedy. When a subcontractor or supplier goes unpaid on a private project, one possible remedy is to file a lien against the land or improvements. The lien remedy has its limits, however. If you start work after the project has gotten

Following the market crash in 2008-09, the $2.8 billion Fontainebleau development in Las Vegas was halted with 70 percent of the construction completed. Naturally, numerous mechanic’s liens were filed by contractors, subcontractors, professionals and suppliers ("claimants"). In the bankruptcy proceeding, the lenders asserted novel and potentially legally destabilizing theories against the claimants’ rights: a.) the

Lien claims can be an unfortunate reality of even the best-laid development plans. Owners or developers facing a lien claim can be held liable to lenders, landlords or investors for liens filed on project property if they are not careful. When faced with lien claims, I recommend that owners and developers ask five questions:

  1. Is

Under Oregon law, a construction lien generally has priority over a trust deed or mortgage on an improvement.  ORS 87.025(1).  If a construction lien claimant has priority over a trust deed or mortgage, the construction lien claimant will get paid from the proceeds of a foreclosure sale before the trust deed holder or mortgagee.  Having

In Pioneer Construction, Inc. v. Global Investment Corp. (Dec. 21, 2011, No. B225685), Cal.App.4th [2011 WL 6382113], the Second District Court of Appeal recently affirmed a timely topic in this depressed construction market:  lien claimants must protect their rights, and buyers of property out of bankruptcy must verify the validity of lingering lien claims.