New Washington Case Strictly Construes Lien Statute and Rejects Warranty Work as Basis to Extend Lien Filing Period

In its March 11, 2021 opinion, Division Three of the Washington Court of Appeals considered whether the 90-day period to record a claim of lien is extended by a contractor performing work after substantial completion to correct nonconforming work – usually referred to as “warranty work.”  In the case of Brashear Electric, Inc. v. Norcal … Continue Reading

Washington Supreme Court Reverses Williams

In Williams v. Athletic Field, Inc., 155 Wn. App. 434 (2010), the Washington Court of Appeals ruled that a lien filing was invalid because it was not properly acknowledged. This decision created a stir among Washington construction lawyers, because the lien claimant had used a lien filing service which in turn had used a form … Continue Reading