Oregon law requires a lien claimant to perfect its lien by recording it within 75 days of ceasing to “provide labor, rent equipment, or furnish materials or 75 days after completion of construction, whichever is earlier.” An unpaid contractor must record its lien 75 days after completion of its major contract work and removal of … Continue Reading